Add release checklist issue template; Document some of our timelines around releases (#1538)
* Add a spec release checklist issue template because I'm tired of copy/paste * Document a chunk of our release approach This should probably go elsewhere, but here is fine for now as a SCT-referenced doc/content. * changelog * Brief clarifications
This commit is contained in:
parent
089d209047
commit
fbb8a789f6
3 changed files with 80 additions and 0 deletions
34
.github/ISSUE_TEMPLATE/release.md
vendored
Normal file
34
.github/ISSUE_TEMPLATE/release.md
vendored
Normal file
|
@ -0,0 +1,34 @@
|
|||
---
|
||||
name: [SCT] Release checklist
|
||||
about: Used by the Spec Core Team to create a new release.
|
||||
title: 'Matrix 1.X'
|
||||
labels: 'release-blocker'
|
||||
assignees: ''
|
||||
|
||||
---
|
||||
|
||||
<!-- ------------------------------------------------------------------------ -->
|
||||
<!-- Please asssign the release coordinator (probably yourself) to this issue -->
|
||||
<!-- ------------------------------------------------------------------------ -->
|
||||
|
||||
Date: **Thursday, May 25, 2023** <!-- CHANGE ME -->
|
||||
Previous release: <!-- LINK TO LAST RELEASE'S CHECKLIST -->
|
||||
|
||||
Preflight checklist ([release steps](https://github.com/matrix-org/matrix-spec/blob/main/meta/releasing.md)):
|
||||
|
||||
* [ ] Blog post written
|
||||
* [ ] Check for release blockers that may have been missed
|
||||
* [ ] Review/fix the changelog
|
||||
|
||||
Release checklist ([release steps](https://github.com/matrix-org/matrix-spec/blob/main/meta/releasing.md)):
|
||||
* [ ] Branch stuffs
|
||||
* [ ] Github release artifact
|
||||
* [ ] Published to spec.matrix.org
|
||||
* [ ] All links work
|
||||
* [ ] Publish blog post
|
||||
* [ ] Announce in #matrix-spec, client developers, HS developers, SCT office, and other rooms as warranted
|
||||
* [ ] Post to Twitter/Mastodon
|
||||
* [ ] Close this issue
|
||||
|
||||
Known release blockers:
|
||||
* [ ] <!-- Issue/PR link -->
|
1
changelogs/internal/newsfragments/1538.clarification
Normal file
1
changelogs/internal/newsfragments/1538.clarification
Normal file
|
@ -0,0 +1 @@
|
|||
Document more of the spec release timeline/process.
|
|
@ -4,6 +4,51 @@ The whole specification is now released as a single unit/artifact. This document
|
|||
the process for releasing the specification and a description of how the (public)
|
||||
machinery works.
|
||||
|
||||
## Timeline
|
||||
|
||||
The spec is released each calendar quarter. The target release dates are within the
|
||||
following ranges:
|
||||
|
||||
* Q1: January 20-27 (critically, before FOSDEM).
|
||||
* Q2: May 20-27.
|
||||
* Q3: August 20-27.
|
||||
* Q4: November 1-15 (before recurring November conflicts, like IETF).
|
||||
|
||||
The SCT aims to have dates picked out by:
|
||||
|
||||
* Q1: January 10.
|
||||
* Q2: May 1.
|
||||
* Q3: August 1.
|
||||
* Q4: October 15.
|
||||
|
||||
When a release date is picked, a [checklist](https://github.com/matrix-org/matrix-spec/issues/new?assignees=&labels=release-blocker&projects=&template=release.md&title=Matrix+1.X)
|
||||
issue is created to track details of the release. Release blockers should continue to
|
||||
be accepted up until 7 calendar days prior to the release date.
|
||||
|
||||
**Release dates are not promises.** The SCT reserves the ability to change, cancel,
|
||||
postpone, etc a release for any reason. Do not rely on a release happening on a given
|
||||
day until the release has actually happened & blog post published.
|
||||
|
||||
Once a release is scheduled, the SCT will begin planning what the next release is
|
||||
expected to look like. The plan should be included in the spec release blog post,
|
||||
and be ready for exeuction on spec release day. Plans are guides and not promises.
|
||||
|
||||
A blog post for the SCT members to review should be ready at minimum 1 week before
|
||||
the target release date. 1-2 days before the release itself, the prerequisite steps
|
||||
below are executed to ensure the spec release can go ahead.
|
||||
|
||||
## Release composition
|
||||
|
||||
*This section is a work in progress.*
|
||||
|
||||
Mentioned above, the SCT aims to have spec releases quarterly. Each quarter has a
|
||||
slightly different theme to it:
|
||||
|
||||
* Q1: Massive feature release, if possible. This generally happens thanks to FOSDEM.
|
||||
* Q2: Regular feature release, if possible.
|
||||
* Q3: Momentum-continuing feature release, if possible.
|
||||
* Q4: Preferably a maintenance release, but will accept features per normal.
|
||||
|
||||
## Prerequisites / preparation
|
||||
|
||||
First, can we even release the spec? This stage is mostly preparation work needed
|
||||
|
|